Ortega Interchange Construction Timeline
Project Schedule:
Draft PR/ED Actual 3/28/08
Fial PR/ED Actual 6/1/09
35% Design/RW Rqmnts January 2010
Bridge Type selection August 2010
65% Design January 2011
95% Design July 2011
PS&E to HQOE: Decemeber 2011
Right of Way Cert: March 2012
Ready to List: April 2012
CTC Funds Vote: May 2012
Advertise: June 2012
Bid Opening August 2012
Award Contract: September 2012
Approve/Start Contract: October 2012
Construction Complete: November 2014
Contract Costs: Programmed
Construction Estimate: $38,814,000
Right of Way Estimate: $28,753,000
|
|
|
|